pareto graph in JMP-please help
Hi ALl
Iam trying to draw a Pareto graph in JMP with the following columns in my excel. Can someone help me how to draw a pareto that has cost and cumulative percentage?
Data:-
PONC Summary Cost ($) Cum%
Operator Error 250000 65.8%
Packaging/Hanlding 34013 74.8%
Assembly Realted 25000 78.2%
Equipment function 32000 78.3%
Maintenance 18000 100%
please help me for that sample data
thanks,
Accepted Solutions
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Get Direct Link
- Report Inappropriate Content
Re: pareto graph in JMP-please help
You can click on a bar in the Pareto plot and choose "Causes->Move to Last".
-Jeff
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Get Direct Link
- Report Inappropriate Content
Re: pareto graph in JMP-please help
I the Pareto Plot dialog you can use PONC Summary in the Y, Cause role and the Cost column in the Freq role.
You'll get this pareto plot.
-Jeff
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Get Direct Link
- Report Inappropriate Content
Re: pareto graph in JMP-please help
Thanks a lot. In pareto graphs, how do we get the "OThers" column at the end of the graph? Thanks
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Get Direct Link
- Report Inappropriate Content
Re: pareto graph in JMP-please help
You can click on a bar in the Pareto plot and choose "Causes->Move to Last".
-Jeff