What is the formula for Control Chart Sigma when you do a capability analysis after you perform a presummarize control chart

11303_JMP Capability training.jpg

1 REPLY 1
txnelson
Super User

Re: What is the formula for Control Chart Sigma when you do a capability analysis after you perform a presummarize control chart

I have scanned the JMP Book "Quality and Process Methods" and did not find a definitive answer, but my best estimation is that it is the In-Control Sigma.  Here is an excerpt from the book: