Hi,
I struggle to find a way to add a line to connect all points in I-MR chart. The option "Show connect line" is checked but still nothing.
Anyone has an idea why ?
Thanks
What version of JMP are you using? I'll start with I don't know why (I know not helpful), but try to create the IMR chart using Analyze>Quality and Process>Legacy Control Charts>IR and see if the chart looks OK. If that has the connecting lines, you might submit the problem to JMP tech support support@jmp.com
What version of JMP are you using? I'll start with I don't know why (I know not helpful), but try to create the IMR chart using Analyze>Quality and Process>Legacy Control Charts>IR and see if the chart looks OK. If that has the connecting lines, you might submit the problem to JMP tech support support@jmp.com
Using JMP Pro 16. I will try your option. Thanks
It worked using your solution. Will submit the problem. Thanks again