How to connect points with line in I-MR chart ?

Hi,

 

I struggle to find a way to add a line to connect all points in I-MR chart. The option "Show connect line" is checked but still nothing.

Anyone has an idea why ?

 

Thanks

1 ACCEPTED SOLUTION

Accepted Solutions
statman
Super User

Re: How to connect points with line in I-MR chart ?

What version of JMP are you using? I'll start with I don't know why (I know not helpful), but try to create the IMR chart using Analyze>Quality and Process>Legacy Control Charts>IR and see if the chart looks OK.  If that has the connecting lines, you might submit the problem to JMP tech support support@jmp.com

 

"All models are wrong, some are useful" G.E.P. Box

View solution in original post

3 REPLIES 3
statman
Super User

Re: How to connect points with line in I-MR chart ?

What version of JMP are you using? I'll start with I don't know why (I know not helpful), but try to create the IMR chart using Analyze>Quality and Process>Legacy Control Charts>IR and see if the chart looks OK.  If that has the connecting lines, you might submit the problem to JMP tech support support@jmp.com

 

"All models are wrong, some are useful" G.E.P. Box
LogitTurtle576
Level III

Re: How to connect points with line in I-MR chart ?

Using JMP Pro 16. I will try your option. Thanks

LogitTurtle576
Level III

Re: How to connect points with line in I-MR chart ?

It worked using your solution. Will submit the problem. Thanks again