Hi Martin Y here:
I have a question about how to run screening in mixture design.
Below is an example:
Cement 1: 36%
Cement 2: 15%
gypsum: 5%
accelerator: 0.2%
retarder: 0.1%
additive 1: 0.2%
additive 2:0.3%
filler 1: 20%
filler 2: 23.2%
Total 100%
Suppose I want to run a screening test first, I want to pick 5 or 6 factors, the ingredients in the formulation all can not be zero. So all the ingredients have lower and upper limit.
So basically it will be a Etreme vertices design.The problem is: Etreme Vertices for 6 factors is huge.
Is there any more economical screening design for mixture design? what I want is:
1. screening design ( 5 or 6 factors with lower and upper limit) without replicates.
2. Exteme design ( 3 or 4 factors with lower and upper limit) with replicates.
Thanks!
Martin Yang