LouV,
We narrowed down the factors available on the Ishikawa diagram (originally had 24 possibilities) to the most likely candidates through engineer's process knowledge + multi-voting. The multi-voting gave each team member 100 points to "assign" to factors based on their knowledge of the process under consideration. Then the highest voted factors were selected for DOE-Screening. Just after that I stumbled upon DSD. Brilliant stuff indeed!
I am not understanding your comment, "Also, if appropriate, always remember to include water as a factor since its understanding is probably responsible for 50% of my raises over the course of my career." We aren't using water in our process.
To build the 4 factor DSD, I made a (JMP7) Screening Design for the 4 factors. Then added one center point. After [Make Table], I manually changed two of the rows to match the DSD 'pattern'. However, since Ryan Lekivetz (see above) suggested using the 6 factor DSD, I am going to revisit the DSD design I was using and try to wrangle it (Augment Design?) into a 6 factor version DSD. Can JMP handle this?
Thanks for all the helpful information!
RB